2019-07-01/02 MEA HV commissioning

documents/MIO_HV_commissioning/IMG_2112_fix.jpg

2019/07/01 MEA1 data

documents/MIO_HV_commissioning/bepi_darmstadt_data_mea1.png

2019/07/02 MEA2 data

documents/MIO_HV_commissioning/bepi_darmstadt_data_mea2.png

Documents

Planning

Dear colleagues,

In the coming two weeks, we will perform Mio delta commissionning: MPPE
HV check out.
It is one of most critical operations for Mio, but it will be also an
exciting time for us!

The summary information is shown in attached excel file :
Summary_table_Mio_delta-commissioning_190621.xlsx

You can also find the connection information as follows.
If you have any questions, please let me know.

Cross fingers!


=== Zoom

https://zoom.us/j/3256594488
Meeting ID: 325 659 4488
Password: miohv

=== MMO system QL info

Use 31_MMO_X_RL_MAL (MLG: 24-28 June 2019)
Use 32_MMO_X_RL_NOR (NNO: 01 July - 08 Aug 2019)

=== PI-QL info

Use SOCKFILE.X.STPSTRG_MAL and ANTID=162 (MLG: 24-28 June 2019)
Use SOCKFILE.X.STPSTRG_NNO and ANTID=163 (NNO: 01 July - 08 Aug 2019)

=== Meeting time at the ESOC security gate

04:15 CEST on 24 June (Mon)
04:15 CEST on 25 June (Tue)
04:15 CEST on 26 June (Wed)
04:15 CEST on 27 June (Thu)
04:15 CEST on 28 June (Fri)

14:30 CEST on 01 July (Mon)
14:30 CEST on 02 July (Tue)
14:30 CEST on 03 July (Wed)
12:00 CEST on 04 July (Thu)
12:00 CEST on 05 July (Fri)

Best regards,

Go